Pebble Hill - Betchworth - road re-opened



Pebble Hill Road mains replacement

Thursday 22 January
As Network Rail have now delayed their maintenance work at the Betchworth rail crossing scheduled for this weekend, Pebble Hill Road will be reopened at 5pm on Friday 23 January, two days earlier than we reported last week. 
This mains replacement works will now progress along the A25 for approximately 1.5 miles towards Dorking. Fortunately, the road is wide enough at this point for the majority of the works to be carried out without interrupting traffic flow. At the same time, our mains replacement work will continue in the fields adjacent to Pebble Hill Road which will include tunnelling under the railway line. 
We apologise in advance that we will have to close Pebble Hill Road once more around the end of March to decommission the old water main. We are in discussions with Surrey Highways about the timing and duration of this closure which we hope will take place during the Easter school holidays.  We will confirm the dates as soon as we can and publicise them through local community channels, the media and on our website www.waterplc.com/pebblehill
We would like to thank all drivers, residents and local businesses for their patience and cooperation while we carry out these essential works.
If you have any problems or questions, please contact our Customer Services Team on 01737 772000.